Updates and Information on the Grant Street Project Here

News Release Date
12-01-2025
Back to News
street closed

Please see below for info and details on the project related street closures on Grant Street:

Grant Street sewer project weekly update (12/29): 

  • Weeks of 12/22 and 12/29 update: Work occurred from Monday through Wednesday due to Thursday holidays. The contractor installed replacement sewer pipe on Grant Street, between Yamhill and Pine Streets. Two new sewer manholes were installed on Grant St, at the intersections with Park Street and Pine Street.
  • Week of 1/5 forecast: Work will occur from Monday through Thursday from 8am to 5pm. The contractor will begin to install replacement sewer pipe on W Main Street, between Cunningham and Carr Streets. The north lane of W Main St will be used by the contractor's crew and equipment, while the south lane of the street will be open. Flaggers will be in place to control traffic in the work area. Pedestrian access on the south side of the road will not be impacted by the work.

  • Estimated long-term schedule is outlined below. All dates are subject to adjustment based on work progress and field conditions.

  • December 2025 – completion of sewer replacement on Grant Street, ending at Pine Street.
  • January and February 2026 – Sewer replacement on Main Street, between Cunningham and Yamhill Streets. Trenchless rehabilitation of existing sewer on Main Street, between Yamhill and Pine Streets. Water main replacement on Grant Street, between Carr and Yamhill Streets.
  • March 2026 – new sidewalks on north side of Main Street, between Cunningham and Yamhill Streets. New sidewalk on west side of Cunningham Street. Repaving of north lane of Main Street, between Cunningham and Yamhill Streets. Repaving of Grant Street between Cunningham and Pine Streets

Additional Project Details-

Overnight closures: the sewer replacement work on Grant Street is limited to the hours of 8am to 5pm. During these hours, through traffic is stopped for the one-block length of street under construction. The contractor has requested permission at some locations to maintain a road closure overnight. These overnight road closures stop traffic for a single short section of the block, located between driveways to ensure that all residents still have access to their homes. The map above is the current street closure map with #7 & #8 scheduled for mid-November; tentatively.

These overnight closures let the contractor to leave some equipment in place overnight. By reducing setup time at the beginning and end of each day, the contractor has more productive hours between 8am and 5pm. The City has approved this approach because more productive hours mean the project will be done more quickly and reduce overall impacts to residents. Specific overnight closure locations are being reviewed on a case-by-case basis, and if issues are noted at specific locations, changes will be made.

When there is a closure on your street, you will receive a “door hanger” with contact information for the contractor, and you can always let them know if an overnight closure is impacting access to your home or business. The contractor will maintain pedestrian access overnight whenever possible. Please be careful when you’re near a construction area, even outside of construction hours, and do not cross into areas marked by yellow caution tape.

Also please note, street paving and sidewalk installation is weather dependent and may not happen until March of 2026. 

Share