WWTP Headworks Improvements

Project Status
Complete
Project Type
Sewer

Water Treatment Plan
NW Panther Creek Rd
Carlton, OR 97111

Description

Project Status:     Completed

Project Type:        Capital Project         

 

This project will remove the existing headworks mechanical bar screen, modify the existing channel and install updated facilities.

 

Status Updates

Resources:

Please see the Supporting Files section below for additional project resources.

Schedule:

February 07, 2023:     

     Invitation to Bid announced with a deadline of March 9, 2023

February 16, 2023:       

     10:00 AM non-mandatory pre-bid conference outside the Public Works Building.  Site visit will    be included.

March 14, 2023:

     City Council approves bid award to McClure and Sons for 687,764.00

Files & Resources

Map

Budget

Funding: County ARPA Funds (Design: $112,500); (Construction: $325,000)

Capital Investment Funds (Design: $37,500); (Construction: $325,000)