Water Treatment Plant PLC Upgrade

Project Type:
Capital Project
Project Status: 
Approved

Project Status:      In Progress

Project Type:         Water

Staff Contact:        Bryan Burnham, Public Works Director,

503-852-7575, bburnham@ci.carlton.or.us

 

In October 2021, The City of Carlton is requesting Statement of Qualifications (SOQ) from qualified firms to provide integrator or record service for the City of Carlton, Oregon. The City’s goal is to utilize the support and resources of a single firm to provide these services to facilitate consistency, rapid response to needs, and a standard approach to developing and maintaining the City’s controls and SCADA systems moving forward. The Integrator of Record is to be appointed by the Mayor and City Council and works under the direction of the City Manager.

The City will consider an Integrator of Record contract of approximately three (3) years with an option to renew the contract for an additional two (2) year term upon mutual consent of both parties. The initial contract period is anticipated to start November 1, 2021 and end December 31, 2024.

Status Updates

Resources: Please see the Supporting Files section below for additional project resources.

Schedule:

2021

October 26, 2021

The City sought statements of qualification (SOQ) to provide Integrator of Record services to support our SCADA monitoring and control systems.  The SOQ’s were due on October 26, 2021 at 10AM.  The City received two SOQ’s:

November 2, 2021

The City Council accepted THe Automation Group (TAG) as the integrator of record.