Title 17 DEVELOPMENT CODE
Chapter 17.76 UTILITY LINES AND FACILITIES
17.76.010 Purpose.
17.76.020 Standards.
17.76.010 Purpose.
To provide adequate services and facilities appropriate to the scale and
type of development.
(Ord. 619, 2003)
17.76.020 Standards.
A. The design of all improvements within existing and proposed
rights-of-way and easements, all improvements to be maintained by the city, and
all improvements for which city approval is required, shall comply with the
requirements of the most current adopted Standard Specifications for Public
Works Construction in the City of Carlton.
B. The location, design,
installation and maintenance of all utility lines and facilities shall be
carried out with minimum feasible disturbance of soil and
site.
C. Standards for Water Improvements.
1. All developments
shall be required to be linked to existing water facilities adequately sized to
serve their intended area by the construction of water distribution lines,
reservoirs and pumping station which connect to such water service facilities.
All necessary easements required for the construction of these facilities shall
be obtained by the developer and granted to the city pursuant to the
requirements of the city.
2. Specific location, size and capacity of
such facilities will be subject to the approval of the city engineer with
reference to the most current adopted city of Carlton water master plan. All
water facilities shall conform with existing city pressure zones and shall be
looped where necessary to provide adequate pressure and fire flows during peak
demand at every point within the system in the development to which the water
facilities will be connected. The city will not expect the developer to pay for
the extra pipe material cost for waterlines exceeding eight inches in size.
Installation costs shall remain entirely the developer’s
responsibility.
3. The design of the water facilities shall take into
account provisions for the future extension beyond the development to serve
adjacent properties that, in the judgment of the city, cannot be feasibly served
otherwise.
4. Design, construction and material standards shall be as
specified by the city engineer for the construction of such public water
facilities in the city.
D. Standards for Sanitary Sewer
Improvements.
1. All developments shall be required to be linked to
existing sanitary sewer collection facilities adequately sized to serve their
intended area by the construction of sewer lines which connect to existing
adequately sized sewer facilities. All necessary easements required for the
construction of these facilities shall be obtained by the developer and granted
to the city pursuant to the requirements of the city.
2. Specific
location, size and capacity of such facilities will be subject to the approval
of the city engineer with reference to the most current adopted wastewater
facilities plan. All sewer facilities shall be sized to provide adequate
capacity during peak flows from the entire area potentially served by such
facilities. The city will not expect the developer to pay for the extra pipe
material cost for sanitary sewer lines exceeding twelve (12) inches in size.
Installation costs shall remain entirely the developer’s
responsibility.
3. All properties shall be provided with gravity
sanitary sewer service to a public sanitary sewer system except for parcels
which have unique topographic or other natural features which make gravity sewer
extension impractical as determined by the city engineer. Pumping stations will
be allowed only when it has been demonstrated to the satisfaction of the city
engineer that the development cannot be served by gravity. Maintenance of
residential pumping stations are the responsibility of the property
owner.
4. Temporary sewer service facilities, including pumping
stations, will be permitted only if the city engineer approves the temporary
facilities, including all facilities necessary for transition to permanent
facilities.
5. The design of the sewer facilities shall take into
account provisions for the future extension beyond the development to serve
upstream properties that, in the judgment of the city, cannot be feasibly served
otherwise.
6. All land divisions or other developments requiring
subsurface sanitary sewer disposal systems shall be
prohibited.
7. Design, construction and material standards shall be as
specified by the city engineer for the construction of such sewer facilities in
the city.
8. Prior to acceptance of the sanitary sewer system by the
city, the sewers shall be flushed and inspected by the city as required by the
Standard Specifications for Public Works Construction in the City of Carlton.
All costs shall be borne by the developer.
E. Street Lights. All
developments shall include underground electric service, light standards, wiring
and lamps for street lights according to the specifications and standards of the
city engineer. The developer shall install all such facilities and make the
necessary arrangements with the serving electric utility for the street lighting
system.
F. Private Utilities. All development which has a need for
private utilities, including but not limited to electricity, gas, and
communications services shall install them pursuant to the requirements of the
district or company serving the development.
1. Except as otherwise
provided herein, all utility lines, cables or wires, including but not limited
to those used for electricity, communications services and street lighting which
are on or adjacent to land partitioned, subdivided or developed within the city
of Carlton after the effective date of the ordinance codified in this title,
shall be required to be placed underground. The intent of the city is that no
poles, towers, or other structures associated with utility facilities shall be
permitted on any street or lot within or adjacent to such partition, subdivision
or development.
2. Exceptions. Above ground facilities shall be
permitted for the following in which case the above provisions shall not
apply:
a. Emergency installations or electric transmission lines or to
through feeders operating at distribution voltages which act as a main source of
supply to primary lateral and to direct connected distribution transformers and
primary loads. Should it be necessary to increase the capacity of major power
transmission facilities for service to the area, such new or revised
installations shall be made only on rights-of-way or easements on which existing
overhead facilities exist at the time of such capacity
increase;
b. Appurtenances and associated equipment such as
surface-mounted transformers, pedestal-mounted terminal boxes, meter cabinets,
telephone cable closures, connection boxes and the like;
c. Structures
without overhead wires, used exclusively for fire alarm boxes, streetlights, or
municipal equipment installed under the supervision and with the approval of the
city engineer;
d. Power substations, pumping plants, and similar
facilities necessary for transmission or distribution of utility services shall
be permitted subject to compliance with all zoning regulations and other
applicable land use regulations. The engineer for all such facilities, prior to
any construction being started, shall approve plans showing landscaping and
screening;
e. Certain industries requiring exceptionally large power
supplies may request direct overhead power as a condition;
f. If
existing overhead utilities within or adjacent to the development total less
than one hundred fifty (150) linear feet, the city may allow the applicant to
record an approved improvement deferral agreement, see Section 17.216.030, in
lieu of relocating existing private utilities underground at the time of
development.
3. Information on Development Plans. The developer or
subdivider shall show on the development plan or in his or her explanatory
information, easements for all underground utility facilities. Plans showing the
location of all underground facilities as described herein shall be submitted to
the city engineer for review and approval. Care shall be taken in all cases to
ensure that aboveground equipment does not obstruct vision clearance areas for
vehicular traffic.
4. Future Installations. The owner(s) or contract
purchaser(s) of subdivided real property within a subdivision shall, upon
conveyance or transfer of any interest including a leasehold interest in or to
any lot or parcel of land, provide in the instrument conveying such interest a
covenant running with and appurtenant to the land transferred under which
grantee(s) or lessee(s), their heirs, successors, or assigns mutually covenant
not to erect or allow to be erected upon the property conveyed any overhead
utility facilities, including electric, communication, and cable television
lines, poles, guys, or related facilities, except such facilities as are exempt
from underground installation under this title or are owned or operated by the
city. Such covenant shall require grantees to install, maintain, and use
underground electric, telephone, cable television, or other utility services
used or to be used to serve the premises. A copy of the covenant shall be
submitted with the final plats.
K. Easements for public and private
utilities shall be provided as deemed necessary by the city, special districts,
and utility companies. Easements for special purpose uses shall be of a width
deemed appropriate by the responsible agency. Such easements shall be recorded
on easement forms approved by the city attorney and designated on the final plat
of all subdivisions and partitions. Minimum required easement width and
locations are as follows:
|
Easement Type
|
Minimum Width
|
Location
|
|
Water
|
10 feet
|
(1)(2)
|
|
Sewer
|
10 feet
|
(1)(2)
|
|
Storm (piped)
|
10 feet
|
(1)(2)
|
|
Storm (other)
|
(5)
|
(5)
|
|
Private Utility
|
5 feet (parallel)
|
(3)(4)
|
|
10 feet (other)
|
(1)
|
(1) Centered on utility line
(2) Centered on property line, where possible
(3) All property lines fronting existing or proposed street
rights-of-way
(4) Measured from edge of right-of-way
(5) Determined on a case-by-case basis
(Ord. 619,
2003)
<< previous | next >>